A material request asks for what a crew needs, without a vendor and without a price. A Purchaser or Admin turns it into an RFQ or an order. On some projects an approver signs it off first.
Before you start
You need access to at least 1 project.
You need the materials, the quantities, the date they are needed, and either the delivery address or a plan to pick them up.
Your company may require a cost code, class code or phase code on every line. If your project allows only some cost codes, the picker offers only those.
Steps
Click + in the top navigation bar, then Request Material.
Select the project, then type a name over the request name.
Under Method, keep the truck icon (Delivery), or choose the store icon (Pick Up) if the crew will collect it.
For a delivery, select the Address and set the Requested Delivery Date. For a pick-up, set the Requested Pick Up Date.
Add Attention to and Delivery instructions (or Pick up instructions) if they are needed.
Search for each material, enter the Qty and the Unit, and add a cost code if your company requires one.
Click Add note on a line to explain a substitution, a location or a scope detail.
Click Save to keep it as a draft you can come back to.
Click Request to send it.
What happens next
If your project does not review requests, the status becomes Requested. A Purchaser or Admin picks it up, chooses the vendors and turns it into 1 or more RFQs or orders. The status then becomes Submitted, and every order it produced is listed on the request.
If your project reviews requests, the status becomes Awaiting Approval and the approver is notified. Nothing is ordered while it waits. You can still edit it until the approver decides.
Approved: it is turned into orders straight away (and into an inventory request for anything drawn from a warehouse) and becomes Submitted. You are notified.
Rejected: it becomes Rejected, and the request shows who rejected it and the reason. You are notified. Fix what the reason asks for, then click Restore to send it back for approval.
Once it has been turned into orders you can no longer change the materials on it.
Pick-ups
A pick-up request has no delivery address. The order it becomes is marked as a pick-up, and the purchaser chooses the vendor location on the order.
Notes and limits
A request never carries a vendor or a price. Both are set when it becomes an RFQ or an order.
Click Import Materials to bring a long list in rather than typing it line by line.
If a material is not in your company catalog, the search offers to request it. A Purchaser or Admin reviews it, and the request cannot move on until they do.
Some dates cannot be picked if your company blocks carrier holidays. Hover over a greyed-out date to see which holiday it is.
Delivery details are locked once the request has become an order or an inventory request.
Once you click Request, the cost code and phase code on each line lock. Only a role with Can edit cost code, Can send and update orders or Can send and update RFQs can still change them. A draft keeps both pickers open for everyone. If a code needs changing after you send, ask someone whose role has one of these.
Attach photos, sketches or field notes from Attachments, and add the people who should follow it from Contacts.
Open the menu at the right of the header and click Print for a printable pull sheet for the yard. It prints what is saved, so save your changes first.
Cancelling a request
Click Cancel to stop a request. The button is there while the request is a draft or is waiting to be processed. After it has been processed, it comes back only if every order it produced has been cancelled or deleted as a draft.
Cancelling does not delete anything. The request stays on record with its history, and Restore puts it back: a request that had been sent returns to Requested, and one that was still a draft returns to Draft.
Best practices
Put everything the crew needs on 1 request. A processed request cannot take new lines, so the second thought becomes a second request and somebody in the office merges them by hand.
Name the request after the area or the crew, not the date. The list shows the name beside the request number, and that is how a Purchaser tells 3 requests from the same morning apart.
Attach a photo rather than describing an unusual fitting in the note. The person buying it has never seen the wall you are standing in front of.
Set the date to when you need it on site, not when you want it ordered. The date drives the calendar and what the vendor is asked to hit.