Create a Budget Commitment

Commit a total dollar amount to a vendor for a scope of work, then track it against invoiced spend with Budget Utilization and Remaining.

Written by Gabby Gutman

Commit a total dollar amount to a vendor for a scope of work, then track it against what has been invoiced.

Before you start

  • You need the Admin or Purchaser role by default. Your company can change this per role in Company Settings.

  • Your company must have budget commitments turned on. If Create Budget Commitment is not in the Create menu, ask your Admin, or contact us.

Steps

  1. Open Commitments in the top navigation bar.

  2. Click Create, then Create Budget Commitment.

  3. Select the project, type a name, and select the vendor.

  4. Enter the amount you are committing under Lot Budget.

  5. Add any materials or a tax amount that belong to the same budget. To add materials from a file, click Upload Materials.

  6. Set an expiration date, tags and the delivery details if your company uses them.

  7. Click Save to keep it as a draft, or Submit to confirm it.

  8. In Confirm Submit Commitment, add a commitment number if you use one, then click Submit.

Add materials from a file

On the Materials tab, click Upload Materials and choose how to add them:

  • Upload by Type: a CSV or Excel file that groups materials by type, such as Gear and Wire.

  • Upload by Material: a CSV or Excel file with 1 row per material, its quantity and unit price.

  • Upload PDF: a bill of materials or vendor quote as a PDF. Your company must have PDF upload turned on. If you do not see it, ask your Admin, or contact us.

What happens next

The commitment moves to Confirmed. Its header reads as a sum: Lot Budget + Materials Budget + Tax = Total Budget. Beside it you see Invoiced, Remaining, Budget Utilization and Total Items.

  • Budget Utilization is the share of Total Budget that has been invoiced. An order does not move it until its invoice arrives. It turns orange at 80% and red past 100%.

  • Remaining is Total Budget less Invoiced. It stops at 0, and a warning icon appears when the budget has been exceeded.

Notes and limits

  • Once an order is linked to the commitment you cannot change the vendor.

  • Lines stay editable after you submit. Change them and click Update. You cannot lower a line below what orders already draw on it, or remove it.

  • Close the commitment when the budget is spent. Existing orders stay linked to it, and you can reopen it later.

Best practices

  • Do not read Budget Utilization as what you have ordered. It counts invoiced spend only, so a large order that has not been invoiced yet does not show. Check the commitment's orders before you place another one.

  • Settle the vendor before the first order. It is fixed once an order is linked.

  • Set an expiration date if the price you agreed has one. It shows in the Expiration Date column, so you can see it without opening the commitment.

If this doesn't work

Start a chat from the Messenger in the bottom-left of this page, or email help@subbase.io. Include the order or project number and what you expected to happen.