Skip to main content

How to schedule ads with ad launcher?

This article will guide you through giving an ad a start and end date before you launch it.

Written by Team adnova

An ad schedule tells Meta when an ad should start and stop running. Set it in the launch table and the ad goes out with those dates already on it. These timings are based on the account's time zone.


​

1. Load your creatives
On Launch, click Load Creatives

Select the creatives you want and confirm with Load N Creatives.


​

2. Pick ad sets from a Sales campaign
Scheduling is a Sales objective feature. Every ad set on the row has to belong to a Sales campaign - one that is not leaves the column switched off.


​

3. Find the Ad Schedule column
Scroll the table right. Ad Schedule sits between Promo Code and App Store Redirect. A row that cannot be scheduled shows a hyphen ( - ) instead of the date boxes.


​

4. Choose the dates
Click Select start date and Select end date and pick the day and time for each. The end date has to be after the start date.


​

5. Launch, or clear the schedule
Click Launch Ads and the ad goes out with its schedule. To drop the dates again use Remove schedule in the cell - an empty cell launches the ad the normal way, starting straight away.


​

Good to know

  • Leave the cell empty and nothing changes - the ad launches as it always has.

  • If you later swap the row to an ad set that is not on a Sales campaign, adnova clears the dates, so a stale schedule is never sent.

  • Bulk Edit carries Ad Schedule, so the same dates can be written to every ticked row at once.

  • The same column is on both Partnership Ads tables.

  • The schedule belongs to the ad. The ad set's own start and end dates still apply on top of it.