Company working days on the Assignar dashboard tell the Scheduler which days of the week your crews normally work. New orders, extended orders and pushed shifts skip the other days unless you choose otherwise. Admins with the Settings user access module can change them. The default is Monday to Friday.
Set your company's working days
To set your company's working days on the Assignar dashboard:
Go to Settings > View/Edit Settings.
Open the Order settings tab.
Under Company Working Days, tick the days your company normally works and untick the others.
Save the change. The dashboard shows "Successfully updated setting: Company Working Days".
Where working days are used in the Scheduler
The setting's own description on the Assignar dashboard says: "By default, when creating orders, days that are not selected will not have shifts created. If needed you can override when scheduling." These Scheduler actions follow your working days:
Creating an order or task: non-working days start unticked in Task dates. See How do I create an order in the Scheduler?.
Extending an order: the confirmation offers Schedule onto non-working days ("View/Edit settings to configure company working days"). See How do I change an order's dates and duration in the Scheduler?.
Push Shifts Forward, Add new task and Move orders: each has a Schedule onto non-working days (or Schedule on non-working days) option. See How do I push shifts forward in the Scheduler? and How do I move several orders at once in the Scheduler?.
Schedule a weekend shift once
To schedule work on a non-working day without changing your company's working days, tick the day in the task's Task dates when you create or edit the order, or tick Schedule onto non-working days when you extend or push the order. The setting only changes what is ticked by default.