How do I manage activities (cost codes) on the dashboard?

Activities are the kinds of work workers log time against, such as Excavation, Demolition or Travel.

Activities are the kinds of work workers log time against, such as Excavation, Demolition or Travel. Many companies use them as cost codes. On the Assignar dashboard you add, change and archive activities, link each to a pay code, and decide whether its hours count as worked time for overtime. You need Timesheets and Dockets in your User Access settings.

Your company can rename some words in Assignar, so you might see a different word for Activity.

Add an activity on the dashboard

To add an activity on the Assignar dashboard:

  1. Go to Work Planning > Activities.

  2. Click New Activity. A panel opens.

  3. Type the Activity Name, for example "Excavation". It's required and must be 100 characters or less. Activity ID is filled in for you ("Auto-generated").

  4. Fill in what you need:

    • External ID: an ID from another system you import from. Leave it blank if you're not sure.

    • Unit of Measure: for example m3. Needed if you want to track progress against this activity in a Site Diary. 20 characters or less.

    • Counts toward worked hours: Yes or No. Choose No for time that shouldn't count toward paid hours or overtime, such as unpaid travel. Some companies also see Subtract.

    • Pay Code: the timesheet code paid for this activity.

    • Sort Order: the order in the mobile app's activity list. 0 shows first, then 5, 10 and so on. It must be a whole number, 0 or more.

  5. Click Save.

The dashboard shows "Activity created successfully".

Activities list with the New Activity panel open

Edit, archive or unarchive activities

On the Activities page of the Assignar dashboard, the list shows ID, Name, Unit, Pay Code, Counts as work, Sort Order and Last Modified. Filter with All, Active or Archived, and search with Search Activities....

  • Edit: change the fields and click Save ("Activity updated successfully").

  • Archive: "This Activity will be marked as inactive and hidden from most views." Workers can no longer choose it.

  • Unarchive: makes an archived activity available again.

  • To archive several, tick them and choose Archive Activities.

How activities affect workers and overtime

Related articles