You can rank the suppliers you prefer to hire from for each task on the Assignar dashboard, so everyone knows who to call first when you need to cross-hire. The ranking is set on the task, not on the supplier, so one supplier can be first for one task and third for another. You need the Suppliers and Edit Supplier Ranking user access modules.
A task is a type of work your company schedules, such as Operator. The old help centre called tasks roles, and your company can rename some words in Assignar, so you might see Role instead of Task. This article uses the default words.
Before you start
The suppliers must already exist. See How do I add and manage suppliers on the dashboard?.
Supplier ranking must be switched on for your company. If the Suppliers tab is missing from the task page, ask your Assignar account manager.
You need Suppliers and Edit Supplier Ranking. Read Only users can't open the page where ranking is set.
Rank suppliers for a task on the dashboard
To rank suppliers for a task on the Assignar dashboard:
Go to Resources > Tasks.
Click the task, for example Operator. Its details open in a panel.
Click the launch icon beside the task name at the top of the panel. The older task page opens in a new browser tab.
Click the Suppliers tab.
Click in Add more, start typing a supplier's name and pick it. You can pick several.
Click Add Supplier(s). Each supplier is added to the list with its rank number.
Drag a row by its handle (three lines) to move it up or down. The top row is rank 1, your first choice.
Click Save suppliers.
The dashboard shows "Ranks have been saved succesfully". If it shows "An error occured", the ranking wasn't saved: try again.
Remove a supplier from a task's ranking on the dashboard
To take a supplier off a task's ranking on the Assignar dashboard, open the task's Suppliers tab as above, click the red minus button at the end of the supplier's row, and click Save suppliers. The suppliers below it move up one rank. The supplier itself isn't changed.
Why can't I rank suppliers on the dashboard?
These are the common reasons on the Assignar dashboard:
"You do not have permissions to view/edit supplier ranking." Your user doesn't have Edit Supplier Ranking. Ask an admin to add it.
There is no Suppliers tab on the task page. Supplier ranking isn't switched on for your company, or you don't have the Suppliers user access module.
There is no launch icon on the Tasks panel. Your user is Read Only.
A supplier isn't in the Add more list. It hasn't been added under Project Data > Suppliers yet.