Every order on the Assignar dashboard has a status.

Every order on the Assignar dashboard has a status. The status shows which stage the job is at, decides whether workers are told about their shifts, and, for Confirmed and Invoiced, stops the order's dates from being changed. This article explains all eight order statuses, including Invoiced. Anyone who can edit orders can change a status.

Your company can rename some words in Assignar, so you might see a different word for Order. Status names can't be renamed.

The eight order statuses

Assignar has eight order statuses. They are fixed: you can't add, remove or rename them. The table below shows each status, its colour on the Orders list, and what it means.

Status

Colour

What it means

Pending

Orange

The order is being planned. Use it while you add tasks and allocate workers and assets. Workers are not notified about shifts on a Pending order.

Confirmed

Green

The order is going ahead. Workers are notified about their shifts and can confirm or decline them in the Assignar mobile app. The order's dates are locked.

In Progress

Blue

Work on the order has started. Workers are notified about their shifts and see them in the mobile app, as for Confirmed. Dates can still be changed.

Completed

Grey

The work is finished.

Invoiced

Pink

Your accounts team has billed the client for the order. The order's dates are locked.

Declined

Red

The job was cancelled or the client turned it down. Use it to keep a record of jobs that didn't go ahead.

New

Teal

The order was created from the Assignar mobile app and needs checking in the office.

Quote

Purple

The order is a quote that the client hasn't accepted yet.

What "Invoiced" means for an order on the dashboard

Invoiced is an order status on the Assignar dashboard. It records that your accounts team has billed the client for the order. Setting it does not create or send an invoice; Assignar does not bill your clients for you. Like Confirmed, Invoiced locks the order's dates: see "Why can't I change the dates of a Confirmed or Invoiced order?" below.

Which statuses notify workers

Assignar sends shift notifications to workers, and lists their upcoming shifts in the Assignar mobile app, only when the order is Confirmed or In Progress. Plan an order as Pending, then change it to Confirmed when you want workers to hear about it.

Order statuses are different from allocation statuses. An allocation status (pending, confirmed, declined, invoiced, new) belongs to one worker's shifts on the order, and changes when the worker confirms or declines in the mobile app or when you update it on the order's Notify tab.

Change an order's status on the dashboard

You can change an order's status on the Assignar dashboard from the Scheduler or from the Orders page.

  • In the Scheduler: open the order's edit form, choose a new Status and save. See How do I create an order in the Scheduler?.

  • On the Orders page: open the order, choose a new Status on the Order Details tab and click Save Order.

New orders start with your company's default status. An admin sets it in Settings, in the Order group, with Default Order Status.

Why can't I change the dates of a Confirmed or Invoiced order?

The Assignar dashboard locks the dates of an order whose status is Confirmed or Invoiced, so a confirmed or billed job can't move by accident.

  • On the order's Order Details tab, the Start / End fields are greyed out. The information icon beside them says "Dates can be changed only if order is not in confirmed or invoiced status. All allocations and tasks out of new date range will be deleted."

  • In the Scheduler, pushing shifts forward, extending the order or copying a shift to another date shows "Cannot modify Order with status 'Invoiced' or 'Confirmed'."

  • When you move several orders at once in the Scheduler, Confirmed and Invoiced orders are skipped.

To change the dates, set the status to Pending (or another unlocked status), change the dates, then set it back. Changing dates removes any tasks and allocations that fall outside the new date range.