How do I set up progress tracking in the Site Diary on the dashboard?

Progress tracking lets supervisors record how much work was done each day in the Site Diary on the Assignar mobile app, for example metres of pipe laid, against what was planned for the order.

Progress tracking lets supervisors record how much work was done each day in the Site Diary on the Assignar mobile app, for example metres of pipe laid, against what was planned for the order. On the Assignar dashboard you set up what can be tracked on each order. There are two ways, depending on your company's setup.

Track progress by activity on the dashboard

When your company has order progress tracking turned on ("Enable Order Progress Tracking"), supervisors record progress against the order's activities. To set up an order on the Assignar dashboard:

  1. Make sure each activity you want to track has a unit of measure, for example metres or cubic metres. Activities without a unit can't be tracked.

  2. Go to Work Planning > Scheduler and open the order to edit it.

  3. On the Activities tab ("Set your activities & estimated quantities."), add the activities and enter the planned quantity for each.

  4. Save the order.

In the Site Diary on the mobile app, the Progress card lists these as Recommended activities. The supervisor enters the amount done today, in units or as a percentage, with comments and photos. On the dashboard, each Site Diary's Progress section shows Today, Total and Comments for each activity.

The Activities tab of an order with planned quantities.

Track progress with budgeted quantities on the dashboard

If order progress tracking by activity isn't turned on for your company, supervisors record Work Completed against the order's budgeted quantities instead. To set them up on the Assignar dashboard:

  1. Open the order in the Scheduler to edit it.

  2. Under the quantities section, add a Description, a Unit and the Total quantity for Order for each item.

  3. Save the order.

The Site Diary then shows a Work Completed section with today's amount and the total reported so far.

Why can't supervisors see progress in the Site Diary?

If the Site Diary on the Assignar mobile app has no progress card for an order, check on the Assignar dashboard:

  • The order has no activities with a unit of measure, or no budgeted quantities. Add them as above.

  • The Site Diary has no order. Unscheduled Site Diaries may not offer progress. Link the diary to an order first.