A timesheet on the Assignar mobile app records which activities you worked on, which assets (equipment or vehicles) you used, and any allowances you claim, such as travel or meals. This article explains how any worker adds and changes each of these while filling in a timesheet. Your company's admin decides which activities you can choose and whether allowances are shown.
Your company can rename some words in Assignar, so you might see Role instead of Task. This article uses the default words, such as allocation (a day of work you are scheduled for, called an assignment or shift in older help articles), task (called a role in older help articles), activity, asset and allowance.
Add an activity to a timesheet on the mobile app
To add an activity to a timesheet on the Assignar mobile app:
Open the timesheet and find the Activities and Breaks card.
At the bottom of the card, tap Activity. A new row appears, 1 hour long, starting when the last row ends.
Choose the activity: tap one of the suggested activities shown under the row, or tap more... to open the full Select Activity list.
Set the start and finish times. Times move in 5-minute steps, or 1-minute steps if your company has turned on "Select one minute time increments on timesheets".
Tap Apply. The app shows "New activity added".
If the new activity overlaps another row, the app shortens or splits the other row so they don't overlap.
Change or delete an activity on the mobile app
To change an activity on an Assignar mobile app timesheet, tap the activity's name or times, make the change and tap Apply. The app shows "Activity changes applied". Tap Cancel to undo your change.
To delete an activity, swipe its row to the left and tap the red bin icon. The app shows "Activity deleted". A timesheet must have at least one activity before you can save or submit it.
Work past midnight on the mobile app
If an activity on an Assignar mobile app timesheet runs into the next day, the app shows a Next Day divider and a moon icon on that row. When you apply a row that is on another day, the app asks Confirm Overnight Work: "You have entered activity time for another day" and "Confirm to proceed". Tap Confirm to keep it.
When you edit a row on a timesheet with more than one row, a Start date field appears so you can move the row to the next day. A row can't finish later than 11:59 PM on the day after the timesheet's date, and the first activity must start on the timesheet's date.
Which activities you can choose on the mobile app
The Select Activity list on the Assignar mobile app has two parts:
Recommended: activities linked to the order or project you are working on, plus your recently used activities if your company has turned on "Enable Recently Used Activities in Timesheets".
Other: every other activity. Tap Show Other Activities to see them.
If your company has turned on "Assigned Activities Only (Timesheets)" and the order or project has activities linked to it, you can only choose those activities. The Other list is not shown.
Add an asset to a timesheet on the mobile app
To record equipment or a vehicle you used on an Assignar mobile app timesheet:
Find the Assets card and tap the + icon at the top right of the card.
Choose the asset: tap one of the suggested assets shown under the row, or tap more... to open Select Asset. In Select Asset, assets used by your crew on the allocation are under Recommended. Tap Show Other Assets to see the rest, then tap Next.
Used for Whole Shift is switched on, so the asset uses the same times as your timesheet. To enter different times, switch it off and set the start and finish times.
Tap Apply. The app shows "Asset time changes applied".
You can choose more than one asset in a row. They share that row's times. On a timesheet for an allocation, the asset you were assigned is already added.
To delete an asset row, swipe it to the left and tap the red bin icon.
Can I add an asset attachment to a timesheet on the mobile app?
No. On the Assignar mobile app, you can add assets (equipment and vehicles) to a timesheet, but not asset attachments, such as a bucket, trailer or rock breaker. Select Asset lists assets only. An attachment that is scheduled with your asset still shows with that asset on your allocation, but it isn't recorded on the timesheet. To keep a record of an attachment you used, mention it in your timesheet's comments, or ask your office to set the attachment up as its own asset on the Assignar dashboard.
If your task needs an asset on the mobile app
If your company has set your task to need an asset, the Assets card on the Assignar mobile app shows "Asset required for this role." in red until you add one. Save and Submit stay greyed out until an asset is added.
Add an allowance to a timesheet on the mobile app
To claim an allowance on an Assignar mobile app timesheet:
Find the Allowances card and tap the + icon at the top right of the card. The card only appears if your company has turned on "Show Allowances on Mobile".
On Select Allowances, tick one or more allowances. You can search with the Search allowances box.
Tap Next.
On Add Quantity, enter the quantity for each allowance. It starts at 1.
Tap Apply. The app shows "Allowances added".
Each allowance shows on the card with its quantity.
A quantity must be greater than 0, with no more than 2 decimal places and no more than 8 digits in total. If it isn't, the app shows "Invalid quantity" and Apply stays greyed out.
Change or remove an allowance on the mobile app
To change an allowance's quantity on an Assignar mobile app timesheet, tap the allowance on the Allowances card. Edit Quantity opens. Change the number and tap Apply. The app shows "Allowances changes saved".
To remove an allowance, swipe it to the left and tap the red bin icon.
After you check out of an allocation
After you check out of an allocation on the Assignar mobile app, the timesheet's activity and break times are locked while it is Pending Submission. You can still add and change assets and allowances before you submit.
Why can't I apply my change on the mobile app?
If Apply is greyed out on an Assignar mobile app timesheet, a message in red under the row explains why. Common messages:
"Must be greater than 0 minutes": the finish time is the same as, or earlier than, the start time.
"This overlaps with Excavation (7:00 AM - 11:00 AM) in a different timesheet. Change the time so they don't overlap." (with your activity and times): the row overlaps another of your timesheets.
"Excavator 20t - EX01 overlaps with the same asset 7:00 AM - 11:00 AM. Please change the time so they don't overlap." (with your asset and times): the same asset is already recorded at that time.
"The assets you've selected exceed the times of the Timesheet. Please change the time, so it doesn't exceed the times of the Timesheet.": the asset's times are outside your timesheet's start and finish times.
For the full list, see Why can't I save or submit my timesheet on the mobile app?.