Skip to main content
All CollectionsTimelines
Typical build times
Typical build times
Liv Kiernan avatar
Written by Liv Kiernan
Updated over 2 weeks ago

Renovations are unique, but for most Beams kitchen and bathroom projects, the building phase typically takes 4 to 8 weeks, plus an additional 2-3 weeks for snagging (final adjustments). During your project kick-off, you'll confirm an exact timeline with your builder. Meanwhile, the following milestones offer a general guide on what to expect at each stage.

Kitchens

We typically allocate 6-8 weeks for our contractors to complete the build phase of Beams kitchen projects. This excludes a 2-3 week snagging period during which the kitchen will be essentially complete and fully functional.

Below is a detailed timeline of the key milestones and what to expect at each stage.

Milestone 1: Break ground

Break ground is the official start day of construction.

1. Protection & dust control (1-2 working days)

Your personal belongings and other areas of your home are protected by the contractor so that work can begin.

2. Demolition and condition verification (1-2 working days)

Open walls are inspected for unforeseen conditions and the location and feasibility of recessed items verified on site.

Milestone 2: First fix

If you're itching to go on holiday - this would be a great time to do it!

3. Rough-in and work inspection (8-12 working days)

Behind the walls, framing, plumbing and electrical items are installed.

Milestone 3: Second fix

This phase may seem to progress a bit more slowly as the contractor focuses on perfecting the finer details of the space.

5. Cabinetry installation (5-7 working days)

Cabinets are installed which allows the countertop fabricator to confirm exact measurements.

6. Countertop fabrication and installation (7-10 working days)

Countertop is fabricated and installed. Note: a lull in construction may occur while countertops are readied.

7. Finishes, installation & painting (7-10 working days)

The finishes - appliances, backsplash, hardware, and plumbing accessories - are installed. Walls and ceiling painted.

Milestone 4: Snagging

At this stage, the kitchen will be practically complete and fully usable. We recommend regular use to identify any issues or imperfections that may need fixing. It's common to have around 20 snagging items to address.

8. Complete Snagging (14-20 working days)

Any issues are flagged by you and repaired by the contractor.

9. Project sign-off

Once you're completely satisfied with the results!

Bathrooms

We typically allocate 4-6 weeks for our contractors to complete the build phase of Beams bathroom projects. This excludes a 2-3 week snagging period during which the bathroom will be essentially complete and fully functional.

Below is a detailed timeline of the key milestones and what to expect at each stage.

Milestone 1: Break ground

Break ground is the official start day of construction.

1. Protection & dust control (1-2 working days)

Your personal belongings and other areas of your home are protected by the contractor so that work can begin.

2. Demolition and condition verification (1-2 working days)

Open walls are inspected for unforeseen conditions and the location and feasibility of recessed items verified on site.

Milestone 2: First fix

If you're itching to go on holiday - this would be a great time to do it!

3. Rough-in and work inspection (8-12 working days)

Behind the walls, framing, plumbing and electrical items are installed.

Milestone 3: Second fix

This phase may seem to progress a bit more slowly as the contractor focuses on perfecting the finer details of the space.

4. Substrate, waterproofing and tile installation (8-12 working days)

Substrate is repaired, level, flat and ready for tile. Wet areas will be waterproofed and tile will be installed.

5. Finishes installation & painting (4-5 working days)

Fixtures, vanity, medicine cabinet, shower enclosure and accessories installed. Walls and ceiling painted.

Milestone 4: Snagging

At this stage, the bathroom will be practically complete and fully usable. We recommend regular use to identify any issues or imperfections that may need fixing. It's common to have around 20 snagging items to address.

6. Complete Snagging (14-20 working days)

Any issues are flagged by you and repaired by the contractor.

7. Project sign-off

Once you're completely satisfied with the results!

Did this answer your question?