In an order's activities (haul-out, launch, work on land) you need cranes, travel lifts and cradles. In BlueShell this equipment is not assigned one by one by hand: it is booked automatically based on the article's recipe and on the operators' planning. This article explains how it works and where to see the result.
How equipment gets onto an order
The mechanism is automatic and rests on two things:
The article's recipe — on each article you can declare which equipment is needed, for how long and how many. It is explained in the article The equipment recipe on articles.
The operators' planning — when you plan the operators on an activity that uses that article, BlueShell books the recipe's equipment by itself, placing it in the work window planned for that activity.
In practice: you set the recipe once on the article → you plan the work → the equipment books itself at the right times. If you change or remove the operators' planning, the automatic equipment bookings are recalculated or removed accordingly.
The equipment in the order's page
In the planning block of each job, under the operators, there is a row for each booked piece of equipment, with its name and the window (for example “12 Jun 2026 08:00 – 12:00”). The rows are read-only: they follow the recipe and the planning.
The order's “Equipment” page
From the order menu, the Equipment entry opens a calendar page dedicated to that order's equipment. The page is part of the Planning module: if the marina does not have it active, the entry shows the module's presentation page.
It is a calendar view (day, week, 2 and 4 weeks, month; today button), designed to check the equipment's commitments over time.
This order's bookings are coloured by equipment; those of other orders appear dimmed (read-only), so you see at once whether a piece of equipment is already committed elsewhere in the same period.
To see the maintenance downtimes and the closing hours of a piece of equipment use the Board (see The Board (operator and equipment rows)) or The maintenance calendar.
As the page itself says: equipment is auto-booked from the activity recipes when you plan the operators; other orders are shown dimmed.
Moving between orders and equipment
Show orders opens the list of open orders, with a progress bar (activities planned out of total) and a search field Filter by number, customer, boat...: click an order to go to its calendar.
Right-click on a booking: View order opens the equipment calendar of that order; See this equipment opens the equipment's maintenance calendar in a new tab.
How to read conflicts
Conflicts (same equipment on two jobs, maintenance downtime, out of hours, boat over capacity) are flagged by planning when you move or create a job. The use of the same equipment by two jobs at once and the conflict with an equipment maintenance follow the planning setting: with Allow with confirmation (the default) a warning appears with Proceed, with Do not allow saving is blocked. The warning on availability hours and the one on a boat over capacity are instead always only warnings. They are explained in Planning warnings, blocks and settings.
How to change the booked equipment
Since the bookings follow the recipe and the planning, they are not edited directly on the calendar. To change them:
edit the article's recipe (which equipment, when, how many) — see The equipment recipe on articles;
or change the activity's operators' planning (move or resize the work window): the bookings are repositioned accordingly.