Planning has two views of the same reality: the same planned job appears in both, only the way of looking at it changes.
The Calendar
Shipyard → Planning → Calendar and board, then the Calendar button.
It is the classic calendar view (day / week / 2 weeks / 4 weeks / month). On the left there is the column with the order being worked on and its jobs; on the right, the calendar. You drag (or click) a job onto the calendar and the window opens to assign the operators.
Use the Calendar when:
you are planning one order at a time and want to see the days with their time slots;
you need the week/month view to reason about deadlines.
The Board
Shipyard → Planning → Calendar and board, then the Board button.
It is a row-based view: one row for each operator and one for each piece of equipment, with time running horizontally. Each job is a coloured bar; so you see at a glance who is busy and who is free.
Use the Board when:
you want to compare several operators (and the equipment) over the same period;
you need to move work from one person to another;
you want an overview of the whole yard, not of a single order.
What they have in common
The same assignments: a change made in one view is found in the other.
The duration that spreads by itself over the operator's schedules (see the article How long a job takes and how it is spread).
The same overlap and out-of-hours warnings (see the article Planning warnings, blocks and settings).
The ability to move (drag) and resize (pull the edge of) the bars.
A useful difference to know
On the Calendar you always see all the days; on the Board the days the yard is closed are hidden (see Yard and operator schedules).
If Planning does not appear
Planning is a module that can be switched on for each customer. Its entries are always present in the Shipyard menu, if the marina has the Yard module (the Calendar and board entry opens the last view used; whoever can only view orders arrives at the Board, because the Calendar requires being able to edit them). If the module is not active, opening them shows the introduction page Planning for the Yard with the Contact us button. If it is active but there is nobody in the planner yet, the Calendar and the Board take you to the guided setup Set up planning: see Turning on planning: the guided setup.