This is the central idea of planning: you do not draw how long the bar is. You indicate how many hours of work the job takes (the effort) and BlueShell calculates how much room it takes on the calendar, spreading those hours only over the operator's working hours.
Effort is not duration
Effort = the actual hours of work (the ones you write in the window, e.g. 12:00).
Calendar duration = how long the bar is: the hours of work spread over the operator's schedule, so possibly over several days.
The bar is a single, continuous one: it crosses breaks, nights, closing days and the operator's recorded absences, but the work only “counts” in the open slots. The end of the bar always falls within working hours (never in a closed slot).
Example
An operator works 3 hours a day. You assign a job of 12:00 of work (effort):
Day 1: 3 hours → 9 left
Day 2: 3 hours → 6 left
Day 3: 3 hours → 3 left
Day 4: 3 hours → done
The bar starts on Day 1 and ends on Day 4: a single bar four days long, which “skips” the non-working hours in between.
Moving the bar (dragging)
If you drag the bar to another day/time, the effort stays the same: BlueShell only recalculates where it ends, starting from the new start. You move “the same job”, you do not lengthen it.
If you move it to another operator (on the Board), the duration is recalculated on the new operator's schedule, again with the same effort.
Lengthening or shortening the bar (right edge)
If you pull the right edge of the bar, you are changing the effort:
Lengthen → you add hours of work; if you go beyond the end of the shift, the extra hours continue at the first available moment (typically the next morning), not “into the void” of the evening.
Shorten → you remove hours of work.
Example. A bar runs from 10:00 to 12:00 and the operator clocks off at 12:00. If you lengthen it by half an hour, BlueShell does not leave it “half in the void”: the effort becomes 2 and a half hours and the bar continues until 08:30 on the next working day.
Note. Resizing is done from the right edge. The left edge (the start) does not stretch: to change the start, move the bar.
Operators only
The automatic calculation of the duration concerns operators. Equipment follows as a consequence (it is booked according to the operator's work) and does not stretch by itself.
In practice
Want to change how much work is needed? Edit the hours of work (in the window) or pull the right edge.
Want only to move the work in time or to another person? Drag the bar: the effort does not change.