Work planning: frequently asked questions

The most common questions about BlueShell's Work planning: bar duration, moves, schedules, weekends, conflicts and equipment.

I entered 8 hours of work but the bar lasts two days. Is that a mistake?

No, it is the intended behaviour. You indicate the hours of work (the effort); BlueShell spreads them over the operator's schedule. If the operator works few hours a day, those 8 hours take up several days. The bar is a single, continuous one and “skips” the non-working hours. Details in the article How long a job takes and how it is spread.

How do I change how many hours a job takes?

In two ways: open the bar and edit the hours of work in the window, or pull the right edge of the bar. Dragging the bar, instead, only moves it (the effort does not change).

I lengthened a bar but nothing seemed to change: does it work now?

Yes. If you lengthen the right edge beyond the end of the shift, the extra hours now continue at the first available moment (usually the next morning) instead of staying “in the void” of the evening. Example: a 10:00–12:00 bar lengthened by half an hour becomes 2 and a half hours of effort and continues at 08:30 on the next working day.

Why don't I see Saturday and Sunday on the Board?

Because on the Board the days the yard is closed are hidden; on the Calendar you always see all the days. See Yard and operator schedules.

Why are some slots grey?

Grey marks the closed slots: see Yard and operator schedules.

Can I assign several operators to the same job at once?

Yes: in the planning window you can select several operators; one assignment is created for each on the same window.

I moved a job to another operator and the duration changed. Why?

Because the duration is recalculated on the new operator's schedule, with the same hours of work. If the new operator has a different schedule, the bar can come out shorter or longer on the calendar.

Can I put the same operator twice on the same job?

Yes, but in separate windows (for example today and the day after tomorrow). What is never allowed is letting them overlap: in that case the change is cancelled with a warning. It is the only always-blocking rule.

What happens if I plan outside the schedules?

Normally you get a warning and can go ahead with “Proceed”. The administrator can, however, set some conflicts (schedules, overlaps, maintenance, equipment concurrency) to “Do not allow”, turning them into blocks. See Planning warnings, blocks and settings.

How is equipment booked?

By itself, based on the article's recipe, when you plan the operator's work: it does not have to be assigned by hand. How it works is described in the articles Equipment in orders and The equipment recipe on articles.

I don't see the Planning entries in the menu.

The Planning entries, Calendar and board and Workload, are always present in the Shipyard menu (for those who can view orders). If opening them shows the introduction page Planning for the Yard, the module is not active: press Contact us. If Set up planning opens, nobody is in the planner yet: see Turning on planning: the guided setup.

What is the difference between the Calendar and the Board?

The Calendar is for planning one order at a time, seeing the days and slots; the Board shows operators and equipment in rows and is ideal for comparing loads and reassigning work. They work on the same data. See Overview: Calendar and Board.

How do I record an operator's holidays?

Can I plan a whole team?

Yes: in the Plan operators window choose the Team and all its operators are added. One assignment is created for each.

Why is an operator over 100%?

In Operator workload the available hours go down with absences: a job planned during an absence takes the load over 100%. See Workload: boats, operators and jobs to verify.