The Work limits page (Shipyard → Analysis → Work limits) is for the yard office: it shows, month by month, how much of the limit of each article that has one is already planned, so you see in time when a service is full.
1. Setting the limit
The limit is a field on the article's page: Monthly Processing Limit (the help text says: “Set the maximum processing limit for this service in a given month.”). See The article page. An article with no limit does not appear on the page.
2. The page
At the top you choose the year (with Show: last year, the current one, the next) and the month (January to December). Then you find a card for each article with a limit:
Element | What it says |
Workload | The percentage of the limit already planned, with the bar: green below 85%, orange from 85% to 100%, red above 100%. |
Monthly limit | The limit set on the article. |
Planned | How many jobs of that article are planned in the month. |
Left | Limit minus planned; in red if negative, that is if you have gone over the limit. |
How Planned is counted: these are the jobs (not the sub-jobs) of that article whose planned start or end date falls in the chosen month.
On each card:
View product opens the article's page.
View planning opens the article's trend: the twelve months of the year, each with the number of planned jobs, and the list of jobs of the chosen month (order, customer, boat, planned dates, notes). From the Article selector you move to another article; Back to workload takes you back to the page.
If something is wrong
“No product has a maximum monthly processing limit.” — no article has the limit set. The Go to products button opens the list: set the limit on at least one article.
See also: The article page and Overview: Calendar and Board.