Skip to main content
Complete a scheduled action

Check off the work as complete

K
Written by Kevin Conard
Updated over 3 years ago

You've set up the action and added the action details, now all you need to do is check the action and the day complete. When you check all the actions you've set up as complete, the 'Mark this Culture Track complete for today' will appear. Check the box and the actions will be locked and the culture track will move to the next day. If you need to make any changes to the actions or action groups, uncheck the day and then the actions.

Did this answer your question?