All Collections
Orders
Withholding Payments and Settling Withholdings
Withholding Payments and Settling Withholdings

Settle orders on a project that are awaiting release

P
Written by PX360 Support
Updated over a week ago

Tracking costs that need to be withheld can be messy and confusing but PX360 provides a simple way to withhold and settle amounts. Costs can be withheld for a variety of reasons:

  • Retention

  • A defect

  • Incomplete work

  • Incomplete delivery

  • A dispute

Note: All withheld costs that are Awaiting Release are withheld from the planning budget's Exhausted Spend until they are settled.

Included in this guide:


How to Withhold Payments

From inside a project, click the Cost tab and then the plus (+) button to expand Supplier Costs. Each cost row needs to be matched to the budget. An orange button on the row means that cost has already been matched. A green button is yet to be matched.

  1. Click the green match button in the appropriate cost row

  2. Check the correct box on the popup (e.g. Budget Allocate, Approved Variation/PSA, Split Allocate, or Work Order) and fill in the information for whichever was chosen (see tables below). Note: click the plus (+) button on the company Work Order to see the breakdown.

  3. Check the Selector box to apply the cost invoice to the correct breakdown row

  4. Click Pay Note & Withheld and complete the form fields (below) that pop up to withhold the payment

  5. Finally, click Submit to send the approval request to the user's email

Budget Allocate / Approved Variation/PSA / Split Allocate

Cost Centre

Cost category for the withholding

Variation Title & Number

(Approved Variation/PSA only)

Enter the name and number of the approved variation or provisional sum adjustment (PSA)

Tasks

Select one or more tasks to withhold costs from those selected

Cost Type

Category of costs; e.g. Material, Contractor, Labour, Equipment

Amount

(Split Allocate only)

Designate the amount to withhold from the allocation

Work Order

Total

Automatically calculated from costs

Withhold Amount

Amount being withheld from payment. Withholding amounts are held from the planning budget's Exhausted Spend. Examples may be incomplete work or defects.

Retention Amount

Amount specific to the contract arrangement for the project. Retention amounts are held from the planning budget's Exhausted Spend.

Payment Amount

Automatically applied depending on the withhold and/or retention amounts above.

Comments

Be descriptive. We recommend adding information for tracking purposes.

Notify User (Email)

The email address of the person responsible for approving the payment.

Awaiting Release Tab

You can view all withheld amounts by clicking Orders on the left side menu, then the Awaiting Release tab. Use the plus (+) button to expand the relevant section and view any withheld costs that require settling.

Settling Withholdings

On the Awaiting Release tab, find the row you want to settle or partially settle. Click the Settle button and review the withheld information on the popup. If needed:

  1. Adjust the withheld amounts

  2. Update comments

  3. Confirm the notification email is correct

Click Submit and you're done. When you go back to the Work Orders tab, you will see any amount marked as Awaiting Release has been removed, and the withheld amount has now been included in your Planning tab budget.

Video Tutorial

Did this answer your question?