The install tracker has a feature that will track and highlight projects that are past due for their estimated completion date.

When both the start date and estimated completion date are entered into a milestone, the estimated completion date will be used to indicate specific projects needing review.

If a customer is highlighted in:

  • Red - the current milestone has passed its estimated completion date

  • Yellow - there are 48 hours or less until the milestone's estimated completion date