A user with Super Admin permissions can set up an estimated completion date for the project milestones on the install Tracker.
To set up an auto completion date, follow the steps below (note: The auto estimated completion date is the number of days after the START DATE that they estimate that milestone will be completed.)
Click Your Roles > Epc > Settings and then on the left hand menu, click "Project Milestones"
Click edit on the milestone you want to adjust
Under the general settings tab, find the auto estimate completion date box.
Input the number of days after the START DATE that the milestone should be completed.
Click save.