How to Assign a Risk to a New Portfolio in the Risk Details Screen

Assign risks to a new portfolio using the Portfolio dropdown in the Risk Details screen.

N
Written by Nigel Groen
Updated over 3 weeks ago

How to Change a Risk’s Portfolio

  1. Go to the Risk Details screen

  2. Click on the Portfolio dropdown near the top

  3. Select a new portfolio to move the risk into

    • The dropdown will only show portfolios the user has access to

    • Admin Users see all portfolios

    • Standard Users see only those assigned to them

What Happens When You Move a Risk

When a risk is moved, the following Bow Tie items are automatically moved with it:

  • Root Causes

  • Mitigations

  • Consequences

This helps preserve risk context and security, as these items often share the same sensitivity as the risk itself.

What If Items Are Shared Across Multiple Risks?

If any Root Causes, Mitigations, or Consequences are shared with other risks, you’ll see a pop-up warning. You’ll be given two choices:

Option 1: Move Items

  • Items are moved to the new portfolio

  • They are removed from any other risks they were previously linked to

Option 2: Copy Items

  • New copies of the items are created in the new portfolio

  • The original items remain linked to other risks

  • Duplicated items will only be visible to Admins or users with access to both portfolios

What Happens to Other Linked Data?

Resource Type

What Happens When Risk Is Moved

Root Causes

Moved (unless shared; user prompted)

Mitigations

Moved (unless shared; user prompted)

Consequences

Moved (unless shared; user prompted)

Action Plans

Not moved – stays in original portfolio

Indicators

Not affected – indicators are not tied to portfolios

Business Areas

Not affected – not tied to portfolios

Strategic Objectives

Not affected – visible based on portfolio access

Note: If a user does not have access to the portfolio containing an action plan or objective, they will not be able to view those elements after the risk is moved.

Applies to: Admin Users, Standard Users

Keywords: move risk, change portfolio, assign portfolio, risk details, bow tie, shared items, action plan access