How to Link Tasks:

To Link tasks in the schedule view in gantterAi simply hit shift and select the two or more tasks you are trying to link.

Then go up to the top toolbar and select the icon that looks like a chain link. Note the one next to it that looks like a chain link with wings is how you can unlink tasks.

Once you hit this and look at these two tasks in your gantt chart you will see the link represented by an arrow connecting the two tasks, signifying they’re relationship.

Now to do this on the board side of gantterAi you simply select a tag and hit the chain icon on the top toolbar and it will bring you to a small popup screen. Select create a new chain and name it then hit save.

Then go to the task you would like to link the previous task to and repeat the process above except this time select add to existing chain. Next select the name of the chain you are adding to then hit save.

Now when you come back to your board you will see a link between the two tasks has been made.