Copy measurements lets you reuse parts and labour from one measurement to another, saving time. It copies all parts, pricing, formulas, and labour to a measurement within the same or in a different stage. Quantities are not copied.
⚠️Warning: Copy measurement is not to be used if there is only one part, it will group together with the original copied part.
Best practice when not using parts and labour would be to use +count and create from scratch.
Click measurement actions
Click copy
Type the new measurement name
Select the option of where to copy to:
Current stage:
(name)Another stage (choose another existing in the project)
Click copy measurement
Changing / updating parts in a copied measurement
When copying a measurement, it will duplicate all parts and labour and group/link all parts together, including the part matching the original description.
If a non-grouped part (different description) is required, the following steps will need to be completed to replace the incorrect part.
Alternatively, delete the incorrect part and re-create a new part.
Original measurement DL - 1 | Copied measurement Under the DL-4 |
| DL-1 part is present under the DL-4 measurement as it was copied from the original measurement.
Styling is also copied. |
To update the copied part / labour:
Click part actions, then parts & settings
Click part actions, then edit
Rename the part from the old name, update pricing or formula
Select: Replace to ensure it is not grouped / linked with the measurement part it was copied from
Click save
(Optional) Update style options then click save
Style is identical to the measurement it was copied from
Click X to close
Updating heights in a copied measurement
If a length has been copied that has additional options of m² and m³, the height / width / pitch MUST be changed.
Copied measurements duplicate all parts and labour and create identical linked / grouped parts matching the original description.
In this example, there is just one item to change, the height of the wall.
ORIGINAL MEASUREMENT 2.4m Single Sided Wall | COPIED MEASUREMENT 5m Single Sided Wall |
| The height of 2.4m is present as it was copied from the original measurement.
Styling is also copied. |
|
|
To update the height
On the copied measurement, click measurement actions then parts and settings
Update measurement unit - Height / depth
Type the correct value in(Recommended) Update the style
Style is identical to the measurement it was copied fromClick save
Click X to close
Updating depths in a copied measurement
If an area measurement has been copied that has additional options of m² and m³, the depth or pitch will need to be adjusted. E.g. This measurement copied the concrete (150mm) for the concrete (100mm) deep. The depth MUST be changed.
Copied measurements duplicate all parts and labour and create identical linked / grouped parts matching the original description.
In this example, there are two items to change:
Update the depth from 0.15m to 0.10m
Replace the part concrete (150mm) with concrete (100mm)
ORIGINAL MEASUREMENT Concrete (150mm) | COPIED MEASUREMENT Under the Concrete (100mm) |
| The Depth of 0.15m is present as it was copied from the original measurement.
Concrete (150mm) part is present under the Concrete (100mm) is present
Styling is also copied. |
|
|
1. To update the depth
On the copied measurement, click measurement actions then parts and settings
Update measurement unit - depth / pitch
Type the correct value in(Recommended) Update the style
Style is identical to the measurement it was copied fromClick save
Click X to close
2. To update the part:
Click part actions on the part to be changed
Click edit
Rename the part from the old name, update pricing or formula
Select: Replace to ensure it is not grouped / linked with the measurement part it was copied from
Click save
Click X to close
Copying measurements in a take-off template
Copy measurements will copy all parts, pricing, formula and labour to another measurement in the same or another take-off template.
Click measurement actions
Click copy
Type the new measurement name
Select option of where to copy to:
Current take-off template:
(name)Another take-off template
Click copy measurement
⚠️Warning: Ensure to follow the above steps if changes are required in grouped parts, heights, depths or pitches.
💻Accessed free training?
Arrange your free training by clicking Help > Send us a Message. Our trainers are ready to help with:
Streamlining workflows
Time-saving strategies
Maximising your subscription
Alternatively, visit the Groundplan Academy here for self-directed courses.