🚨 Module 4 will start by using Project B. Make sure you are in Project B for the following steps. 🚨
Owner Initiated Change Orders
A. Create and Send a Change Order Request Package
The owner of your project has asked you to gather pricing information from your vendors for a potential private office conversion they'd like to add to the project scope. Let's put together a change order request package to get this information for our client!
Using the Project Navigation Menu, navigate to Change Orders.
On the Change Order summary page go to the Change Order Request Packages section and click the Create COR Package button.
Input the following information in the Change Order Request Package Details tab:
COR Package Title: Conversion of Private Office 3303 to Conference Room
COR Package Type: Owner / Client Change
Sources: Meeting Minutes
Change Order Description: Conversion of Private Office 3303 to a standard
six-person Conference Room
Post to ACR: Post to ACR and direct Vendors to Price Only
Click the More icon at the top of the page (three vertical dots), and Save
Navigate to the Requests tab.
Click Add Request to send a request to North Star MEP for pricing. Fill out the following information:
Select Vendor Contract: North Star MEP
Project Cost Code: 0290: MEP Engineer
Click the Calculator to enter the following internal estimate:
Click Save
Send to: Since this is occurring off-system we have no user on the other end
to send the request to. Instead, in a real-world situation, you would
export the PDF version of this request and email it to this off-system
vendor.
Date sent to Vendor: today's date
Click the More icon at the top of the page, and Save.
Scroll down and click Add Request again to send a request to Blackhawk Construction for pricing. Fill out the following information:
Select Vendor Contract: Blackhawk Construction
Project Cost Code: 0605: Construction - Interiors
Click the Calculator to enter the following Estimate:
Click Save
Under Send To, select Patrick Kane (since this vendor is on-system, this COR package will be sent through INGENIOUS.BUILD) *if you don't see a contact option in a dropdown, skip this step*.
Scroll down and click Add Request again to send a request to Legends Design Group for pricing. Fill out the following information:
Select Vendor Contract: Legends Design Group
Project Cost Code: 0210: Architect
Click the Calculator to enter the following Estimate:
Click Save
Under Send To, select Duncan Keith (since this vendor is on-system, this COR package will be sent through INGENIOUS.BUILD) *if you don't see a contact option in a dropdown, skip this step*
Click the More icon at the top of page, and click Save.
When you are ready to distribute the Change Order Request Package, click Send All.
You have now distributed the Change Order Request and await pricing so you can start processing change orders. 💰 Great work!
🚨 You will now switch from Project B to Project C 🚨 The next training activity will cover receiving and inputting vendor change orders while you wait for the vendors to respond to the Change Order Request you just sent. Let's dive in!
B. Process an On-System Change Order for Legends Design Group
From the left hand navigation, select the Change Order module. Find Received Change Orders and select View All. Here you can see change orders you have received from your vendors.
You'll now manage the approval of the $5,000 on-system change order that has
been sent from Legends Design for additional services associated with Graphics and Branding services. Click on the Add Service: Graphics and Branding Change Order received from Legends Design.
Review the Change Order content in the Details tab
Review the cost lines associated with this Change Order in the Cost Details tab
Review the attached backup documentation in the Files tab
Within the Files tab click on the Shared with Me tab
The files will automatically sync and now be found under the ‘My Files’ section of the backup Documentation Section
Navigate to the Approvals tab
Click Approve
Select 'Approved'
Type: YES
Add Note: Approved on {today's date}
Click Approve
Click Record Client Approval
Approved by: ABC Client Co.
Type CONFIRM
Click Record Client Approval
Click Start Contract Amendment
Check the checkbox next to I hereby confirm that I have reviewed this contract amendment and it has been fully executed
Click Execute Contract
Congratulations! You have just executed your first on-system change order! 👏
Processing Off-System Change Orders
C. Process an Off-System Change Order for North Star MEP
Since North Star MEP is working off-system, you have received a change order from them via email and will now upload it into the system to process. ✉️
Using the Project Navigation Menu, navigate to Change Orders.
Under Received Change Orders, click Create Off-System CO.
Input the following information in the Details tab (use attachment as reference North Star MEP Change Order 001.pdf):
Vendor Change Order ID: Add Services 01
Contract: North Star MEP - MEP Engineering
Received From: Mike Madano
Change Order Title: Design Fire Suppression System
Change Order Type: Owner/ Client Change
Source: Meeting Minutes
Change Order Description: See the Vendor’s description in the attachment
Schedule Impact: No
Click Save as Draft at the top of the page
Navigate to the Cost Details tab to enter the vendor cost details for the change order.
Under the Select Quoted Item / SoV dropdown, scroll down and click on Add New Scope
Type "Add Service for Fire Suppression", click Add
Confirm Cost Code is '0290: MEP Engineer'
Input the following Change Order cost breakdown based on the North Star MEP Add Service 01 document using the Add Phase button to add multiple cost lines
Click Save as Draft at the top of the page
Navigate to the Files tab to upload backup documentation for the change order.
Click Save as Draft at the top of the page
Now that you have provided all the detail for the change order, you're ready to go through the approval process. First, click the More icon > Save as Vendor Submission (Pending).
Click Approve at the top of the page.
Select 'Approved'
Type: YES
Add Note: Approved on {today's date}
Click Approved
Click Record Client Approval.
Approved by: ABC Client Co.
Type CONFIRM
Confirm Date Approved
Click Record Client Approval
Click Start Contract Amendment.
Check the checkbox next to I hereby confirm that I have reviewed this contract amendment and it has been fully executed
Click Execute Contract
You have just executed your first off-system change order! 👏 Let's do another one to get some more practice.
D. Process an Off-System Change Order Credit for North Star MEP
The client on your project has removed some scope of work and North Star MEP has submitted a credit of $5,000 to be deducted from their contract. Let's process this credit within INGENIOUS.BUILD!
Navigate back to your Received Change Orders page.
From here, click Create Off-System CO.
Input the following information in the Details tab (use attachment as reference North Star MEP Change Order 002_Credit.pdf):
Vendor Change Order ID: Deduct Services 02
Contract: North Star MEP - MEP Engineering
Received From: Mike Madano
Change Order Title: Deduct - Owner Removed Scope of Work
Change Order Type: Owner/ Client Change
Source: Meeting Minutes
Change Order Description: Credit for deleted scope of work
Schedule Impact: No
Click Save as Draft at the top of the page
Navigate to the Cost Details tab to enter the vendor cost details for the change order.
Under the Select Quoted Item / SoV dropdown, scroll down and click on Add New Scope
Type "Credit for Deleted Scope of Work", click Enter to Add
Confirm Cost Code is '0290: MEP Engineer'
Input the following Change Order cost breakdown. When entering the credit, make sure to type a "-" sign to indicate it is a negative number.
Click Save as Draft at the top of the page
Now that you have provided all the detail for the change order, you're ready to go through the approval process. First, click the More icon > Save as Vendor Submission (Pending).
Click Approve at the top of the page
Select 'Approved'
Type: YES
Add Note: Approved on {today's date}
Click Approved
Click Record Client Approval
Approved by: ABC Client Co.
Type CONFIRM
Confirm Approval Date
Click Record Client Approval
Click Start Contract Amendment
Check the checkbox next to I hereby confirm that I have reviewed this contract amendment and it has been fully executed
Click Execute Contract
The credit is now executed! 💸
Processing Change Order Request Responses
In the first step of this module, we sent out a change order request package to our vendors to gather some pricing information. Let's assume some time has gone by 🕦 and the vendors have now responded with their pricing! We'll take a look and process the incoming information.
E. Process Legends Design Group's Change Order Request
Using the Project Navigation Menu, navigate to Change Orders
In the Change Order Request Packages tile, click View All
Click on the "Conversion of Private Office 3303 to Conference Room" package we created earlier
Click the Requests tab
Click on View Received CO next to Legends Design Group (you may have to scroll down on the page to locate this)
Within the change order, take a minute to click through the tabs and review the information.
Within the Files tab, click on Shared with Me to sync the backup document to your files
Open up the pdf and take a look at the information Legends provided
When you are satisfied with the vendors content navigate to the Approvals tab.
Click Approve
Select 'Approved'
Type: YES
Add Note: Approved on {today's date}
Click Approve
Click Record Client Approval
Approved by: ABC Client Co.
Type CONFIRM
Confirm Approval Date
Click Record Client Approval
Click Start Contract Amendment
Check the checkbox next to I hereby confirm that I have reviewed this contract amendment and it has been fully executed
Click Execute Contract
You have now processed Legends change order for this specific request. Let's go back in and process the other two!
F. Process Blackhawk Construction's Change Order Request
Go back to the Change Order Request you sent out.
Click on View Received CO next to Blackhawk Construction (you may have to scroll down on the page to locate this).
Within the change order, take a minute to click through the tabs and review the information.
Within the Files tab, click on Shared with Me to sync the backup document to your files
Open up the pdf and take a look at the information Blackhawk provided
When you are satisfied with the vendors content navigate to the Approvals tab.
Click Approve
Select 'Approved'
Type: YES
Add Note: Approved on {today's date}
Click Approve
Click Record Client Approval
Approved by: ABC Client Co.
Type CONFIRM
Confirm Approval Date
Click Record Client Approval
Click Start Contract Amendment
Check the checkbox next to I hereby confirm that I have reviewed this contract amendment and it has been fully executed
Click Execute Contract
You have now processed Blackhawk's change order for this specific request. Two down, one to go!
G. Create North Star MEP's Change Order Request
Since North Star MEP is an off-system vendor, they replied to your email request and provided a pdf document with pricing. You'll now be entering this information into the INGENIOUS.BUILD system!
Go back to the Change Order Request you sent out.
Next to the North Star MEP line, click Create Manual CO.
Under Details, some details from the Change Order Request Package will automatically pull in. For the rest, enter the following using the attachment as reference North Star MEP Change Order 003.pdf:
Navigate to the Cost Details tab to enter the vendor cost details for the change order.
Under the Select Quoted Item / SoV dropdown, scroll down and click on Add New Scope
Type "MEP - Office 3303 Change", click Add
Confirm Cost Code is '0290: MEP Engineer'
Input the following Change Order cost breakdown based on the North Star MEP Add Service 02 document using the Add Phase button to add multiple cost lines
Click Save as Draft at the top of the page
Navigate to the Files tab to upload backup documentation for the change order.
Click Save as Draft at the top of the page
Now that you have provided all the detail for the change order, you're ready to go through the approval process. First, click the More icon > Save as Vendor Submission (Pending).
Click Approve at the top of the page
Select 'Approved'
Type: YES
Add Note: Approved on {today's date}
Click Approved
Click Record Client Approval
Approved by: ABC Client Co.
Type CONFIRM
Confirm Approval Date
Click Record Client Approval
Click Start Contract Amendment
Check the confirmation box
Check the checkbox next to I hereby confirm that I have reviewed this contract amendment and it has been fully executed
Click Execute Contract
You have now processed North Star's change order for this specific request. You are all done with this change order request. Let's move on to budget changes!
Processing Budget Changes
H. Process a Master Budget Change
As the project has evolved, you'd like to reallocate $50,000 from your contingency allowance into the construction budget. Let's walk through how to do this!
Using the left hand navigation, select Projects and navigate to Project C.
In the left hand navigation, click on the Master Project Budget/ACR.
Select the Owner Budget Changes tab.
Click Add New Budget Change.
Enter the following information under Details:
Budget Change Category: Contingency Reallocation.
Reason for Change: Budget Scope Gap
Description: Reallocation of contingency funds to construction
Click Next Step
Enter the following information under Budget Line Items:
Click Save as Pending
Click Yes, Save as Pending
Click into the budget change you just created
Click Approve
Select 'Approved'
Type: YES
Add Note: Approved on {today's date}
Click Approved
Click Record Client Approval
Approved by: ABC Client Co.
Type CONFIRM
Click Record Client Approval
Now that the budget change is approved, the budget change amount can now be seen moving $ from '06.1090 Miscellaneous Cost – Project Contingency' to '03.0605 Construction Cost – Construction Interiors' and has moved from the
Pending Budget Changes (Column D) to the Approved Budget Changes (Column
B). Go take a look for yourself by clicking back to the Budget Summary tab!
You have just processed your first budget change! 🔁 Now whenever you need to reallocate money within your budget you'll be ready to make those changes!
📓 To document your completion of Module 4, navigate to the Master Budget/ACR, click the Export icon > Export to PDF> ACR PDF> Rentable> ACR Summary & Detail, and save the pdf to your files. |
You have now completed Module 4. 🎉 You sent out a change order request package, processed off-system change orders, and approved a budget change. Proceed to Module 5.