🚨 Training Module 1 uses Project A. Make sure you are in Project A for the following activities.
Project Set-Up
Let's setup a project in INGENIOUS.BUILD!
A. Update Project Information
Navigate to Project A by clicking Projects> Projects on the Left Hand Navigator
Once taken to the projects list, click on Project A - Your Name
Using the Project Navigation Menu go to Project Settings.
Once in the Project Settings go to the Project Information tab and click the Edit button to update the project information to the following:
Baseline Project Start Date: 9/1/2023
Baseline Project End Date: 01/29/2025
Sector/ Industry: Office
Unit of Measure: Imperial
Rentable Area: 50,000 RSF
Click Save Settings
Go to the Financial Approval Workflows tab to turn off client approval.
B. View Project Directory
Using the Project Navigation Menu go to the Project Directory.
Take note of the pre-populated contacts for each vendor profile
YourCompanyName – Project Manager Contact: YourName
As you add people to the project they will automatically populate to the Project Directory. You can also add people to the project directly from the Project Directory.
You can also indicate the role of a company on a project. Click the edit icon next to Project Role next to your company name
Type Owner and click the green check mark
Cost Codes / Master Project Budget / Templates
C. Master Project Budget / ACR Setup
You will now setup a budget for your project! 💲
Using the Project Navigation Menu or the Project Dashboard navigate to the Master Project Budget / ACR.
Make sure you are in the Owner Budget (not My Budget) tab in the top right-hand corner.
Once you get to the Master Project Budget / ACR you will be prompted to choose a budget type. Select a Single Master Budget by clicking Create Single Master Budget.
You will be prompted to select a template for this budget. Select the Life Cycle Format - Standard Tenant Improvements template by searching for it in the search bar or finding it in the list. This will import the cost code structure for your project budget based on a standard tenant improvement type project. Click Load List.
You will be prompted to confirm your project base currency as USD. Click Proceed.
For the sake of this training please select USD regardless of your region's currency type.
NOTE: The full library of Templates and the master lists from which they are made can be found in the Lists and Templates tab in the Left-Hand Navigator. Project Managers have view only access to the lists and templates. Once using the system for real projects, if there is a template you would like to create or an item you feel should be added to the master list please contact your system administrator. Only system administrators will be able to edit the Lists and Templates.
D. Build the Master Project Budget Detail
Click the [+] indicator on the left of the Category # column header to expand the budget so you can see all cost codes displayed on this Master Budget/ ACR
Find the Cost Code: 02.0210 Architect under Professional Design Services, and click on the “$0.00” in Column ‘A’ Original Budget to open the budget line detail window for this cost code
Click Load from Template.
Load the Architect - Ten Rep Interiors Concept - Ten Rep Interiors Conceptual template by selecting it and clicking Load to import preset budget line details for this cost code.
Enter the associated line item cost values found in the following image:
Click Save to save your progress.
Follow steps 2-6 to fill out the rest of your budget detail with the following information:
Cost Code: 03.0490 Project Management Services
Cost Code: 04.0605 Construction - Interiors
Template: Construction (Base Bldg. and Interiors) - Ten Rep Interiors Conceptual
Delete the Construction - Restroom Upgrades and/or Modifications line item using the trash can on the right end of the line item.
Reorder the line items to look like the following image by dragging each line item by the three horizontal lines on the left side of the line item, and input the following values:
Cost Code: 08.1090 Project Contingency
The total budget at this point should be $5,242,875.00. If your budget total is different than this make sure to double check the numbers that you input into the cost codes referenced above.
Download a PDF of the Budget Authorization.
On the Budget/ACR screen click on the Export icon in the top right corner of the screen.
Click Export to PDF.
Select Budget Approval Authorization PDF > Export > Rentable > Confirm.
E. Approve the Budget
DID YOU KNOW?💡 Approving the budget as "final" locks in the Original Budget values in Column A of the Master Project Budget / ACR.
Click Approval Budget at the top right of the Master Budget/ ACR.
Funding Sources
F. Allocate Funding to the Budget
Create Tenant Funding Source
Using the Project Navigation Menu select Funding
Click the button for Add Fund
Funding Method: Project Specific
Add the Funding Source Name of "Tenant Funding"
Under Provider, select John Smith at ABC
Allocate the entire budget to the Tenant (until we know what the allocation to the landlord will be).
Click Save
Click Add New Fund to save the information entered.
Create New Landlord Funding Source
Click the button for Add Fund
Funding Method: Project Specific
Provider: William Starr at WRS Ownership Partner
Funding Source Name: Landlord Funding
Allocate a portion of the budget to the Landlord
Click Save
Click Add New Fund to save the information entered.
Adjust Tenant Funding Amount
Now that the portion of the budget that will be funded by the landlord is determined we need to adjust the Tenant Funding amount so that the project is not overfunded. Click into the Tenant Funding funding source and select Edit
Reduce the Tenant Funding amount
Click Save in Edit Fund (Total funding should now be $5,242,875.00)
Export Project Budget
G. Export Master Budget Summary and Details
Almost there!👏 You will now export your Master Budget Summary and Details to document completion of the module. Navigate back to the Master Project Budget / ACR
Click the Export Icon at the top of the page
Export to PDF
Select Project Budget PDF and click Export
Select Rentable and click Confirm
Select Budget Summary & Detail and click Confirm
Save this pdf to a folder on your computer. All exports can be emailed to your INGENIOUS.BUILD company administrator if requested.
Take some time to look over the pdf you have exported to understand how the changes you made in the platform reflect on the Master Budget Summary and Details
You now know how to setup and create a budget for your projects. Congratulations, Module 1 is now complete and you are ready for Module 2! 🎉