JACK allows your trades/subcontractors to propose changes to a scheduled item. These proposed changes relate to start date, end date, and duration.
To accept or decline a proposed change, carry out the following steps:
Navigate to Jobs > select relevant job > Project Management > Schedule and double-click a schedule item.
The pop-up Add/Edit Schedule Item will appear on the right. If the trade/subcontractor proposes any schedule changes, they will appear as a proposed change (see image below).
You can accept this change, automatically updating your job schedule and any schedule items linked to it. The trade/subcontractor will be notified.
Alternatively, by declining the proposed change, JACK will notify the assigned trade/subcontractor and will also keep your schedule as it currently is.