3.2.2 Edit Activity in Masterplan Pre-configuration

Edit activity in Masterplan Pre-configuration phase

Leanstation Support avatar
Written by Leanstation Support
Updated over a week ago

After the Masterplan upload, in the pre-configuration phase, an activity can be updated with start date, duration, work progress and work resume date. At any point in time we can rename an activity, change the User/Company in charge and even delete it if it's not necessary. 

  • Double click on the activity bar to access the details.

  • Click on Edit  button (pencil icon)

  • Update the activity (rename activity, edit start date, duration, remaining early start date and work completed (progress))

  • Click the Tick button to confirm.

Fig. Editing an activity with Zero Progress

Fig. Editing an activity with progress


Instead of editing the activity from the detailed view, you can simply click and drag the whole activity or the end date of the activity. Watch the video below to learn how to do so:

Did this answer your question?