3.2.4 Edit Activity Dates

Check out how to edit the start date and duration of an activity in the masterplan pre-config

Leanstation Support avatar
Written by Leanstation Support
Updated over a week ago

The masterplan pre-config phase allows users to re-plan their project and so gives them options to delay or advance activity dates and duration. Since its a re-planning phase, when the dates or duration are changed, the base dates of the activities will also be set to those new dates.

  • Start date and End date of an activity can be set to any dates in the Pre-Configuration stage. 

  • Changing the start date would advance or delay the complete activity 

  • Note: The edited start date and end date of an activity in pre-configuration phase are considered as the base dates throughout the project. 

Did this answer your question?