During the Pre-configuration phase, the portion of work for an Activity which has completed before uploading the Masterplan into Lean PlanDo can be updated. ย
Collect the percentage (%) of work completed and enter it in the Work Completed section under Edit Activity and set the Remaining Work Resume Date (refer to Remaining Early Start Date)ย