3.4.5 Update Activity Constraint Due Date

Advance or Delay Activity Due Date, Delay History

Leanstation Support avatar
Written by Leanstation Support
Updated over a week ago

An Activity Constraint can be delayed or advanced by changing its due-date. If an Approval constraint gets delayed, its due-date can be simply set to a future date to delay the constraint. This can result in delaying the Activity as well.

Any Delay in Activity Constraint will be recorded with the reason for delay and the responsible person for the same. The Delay History tab shown on click of a constraint will display the details of the delay. 

The following steps guide you to Edit Due Date: 

  • Double-click on the Constraint (indicated by a circle and in-lined with it's activity)

  • Click Pencil (Edit) on the last condition of the constraint

  • Select the new due date of the last condition

  • Click Tick

Editing of Constraint due date can be done in both the Masterplan and the Lookahead.

The steps to update a Task Constraint Due Date is similar to updating Activity Constraint Due date, read 4.14 Update task constraint due date to know more.