5.4 Update Task Constraint from Do List

Learn how to change Constraint Status in the Do List

Written by Leanstation Support

The following steps guide you to Update Constraint Status from the Do List:

  • Click on the Constraint drop down button (downwards arrow on the right) (or) Click anywhere on the Constraint bar.

  • This will open up the Conditions of the constraint

  • Hover over each condition to show the Edit (Pencil) button on the extreme right. Click on the Edit to make necessary changes

  • Change the status, due date or assignee of each condition

  • Click Tick to save