Weekly Project Progress - Time (Overview)
Project Progress is represented in the S-curve under Overview. This information will provides an overview of Planned Project Progress vs Actual Project Progress vs Expected Planned Progress in terms of time.ย
Graph:ย
Above Graph indicates the actual progress together with the expected progress of the project against the planned progress.
The planned progress of the project is calculated based on the baseline schedule of the activities.
The actual progress of the project is calculated based on the actual progress input done by the user through the tasks.
The expected progress of the project is calculated based on the planned / expected schedule of the activities. This expected progress is recalculated with every change that is made to the expected dates of the activities.
For detailed information on how the planned progress, the actual progress and expected progress of the project is calculated, click here.