Skip to main content

6.4.1 Critical Project Delays

View Critical Activities, Reasons for Project Delays and Delay Classification

Leanstation Support avatar
Written by Leanstation Support
Updated over 5 years ago

The reasons for delay are required to be input by users during the planning and monitoring process. This reasons are captured and categorized under Insights.
โ€‹

The table below shows the list of top critical path activities that have caused a project delay along with the total days of delay it has gone through and the reasons of these delays.ย 

For illustration:ย 

  • Activity for 2nd Storey Structure (Gym Building) has been delayed 32 days and this delayed activity has stretched the overall project to delay for 26 days. Click on the Activity to see the Delay history for reasons.ย 

Did this answer your question?