Lean PlanDo provides a list of pre-defined reasons that are common causes for work delays in construction projects. Project teams can use this pre-defined list to site the delay reasons whenever a activity or task is delayed in the project. Please find below the delay reasons used in Lean PlanDo: 

  • Access/ space - Site readiness, e.g. the storage area has not been cleared for the next activity on site. 

  • Approval/permit 

  • Client decision - e.g. change in design

  • Contracts - contractual issues causing project delay 

  • Drawings - e.g. lack of drawing information and unable to proceed with work 

  • Defects/rework - e.g. low quality work need to re-work

  • Equipment - e.g. crane is not available 

  • Inspection - additional inspection is carried out by authority 

  • Labor - shortage of labor to carry out the work 

  • Logistics/storage - e.g. lack of storage space will cause the material to be returned to supplier 

  • Material - e.g. delivery of material to site was delayed 

  • Method statement - e.g. additional time for new method statement due to re-design 

  • Minor / temp pre-requisite work

  • Request for Information (RFI) 

  • Safety requirement 

  • Re-scheduling - due to nature of the work sequence on site

  • Unforeseen site conditions - e.g. ground condition 

  • Weather - e.g. stop work due to raining 

  • Others

Delay Classification (Overview)

Delay classification charts show the classification of the reason for delays in activities, tasks or constraints. The charts and tables are sorted based on their occurrences and their impact to the project. Refer images below (click on the images to enlarge). 

Chart 1

Chart 1 sorts delay reasons based on numbers of times they were sighted as the reason for a delay. It can be seen that Materials was the most used delay reason (203 times) followed by Schedule error (171 times).

Chart 2

Chart 2 sorts delay reasons based on the number of days they delayed the project. It can be seen that the major reason for delay in the project is Schedule error that caused the project to delay by 194 days.