6.4.3 Delay Responsibility

Insights on Delay Responsibility

Leanstation Support avatar
Written by Leanstation Support
Updated over 5 years ago

This widget shows the percentage of delay caused by different responsible parties involved in the project.

The responsible party for delay are required to be input by users during the planning and monitoring process. This data are captured and categorized under Insights. 

The following charts show the Delay Responsibility (Overview) 

Chart 1:

Chart 1  shows that the main contractor has contributed to 67.6% of the overall project delay occurrences followed by the sub-contractor who was responsible for 18.7% of the total delay occurrences in the project. 

Chart 2

Chart 2 shows the percentage of project delay in days caused by respective parties in the project. 

In this example, the main contractor has contributed to 95.5% of delayed days in the project.