Activities Performance Analysis (Overview)
Under activities performance, the information on the following top activities that cause the delays can be analysed:
Top Delayed Activities
Top Extended Activities
Top Shortened Activities
Top Early Finished Activities
For illustration (click on the images to enlarge):
Chart 1:
Chart 1 shows the top delayed activities in the project. Activity 2nd storey slab is the most delayed activity with its actual start date delayed by 186 days compared to its base start date. Click on the activity to know more about the delays caused on the activity. An image as given below will be shown
Chart 2:
Chart 2 shows the top extended activities in the project. These are list of activities whose duration got extended the most. In this example, the activity Ground slab soil treatment/lean concrete has extended the longest (i.e. actual duration 146 days vs base duration 9 days) in the project. Click on the activity to know more about the delays on the activity.
Chart 3:
Chart 3 shows top shortened activities. In this example, the activity, Blk 3+4-B1 (archi works) is the most shortened activity, shortened by 40 days compared to its base duration. Click on the activity to know more about the delays on the activity.
Chart 4:
Chart 4 shows the top early finished activities. In this example, activity Cast pile-caps - DT2 finished 325 days earlier compared to its base end date. Click on the activity to know more about the delays on the activity.