All Collections
Lean PlanDo Project
4. Lookahead
4.4 Task Dependencies
4.4.3 Cyclic Dependency Behavior in Lean PlanDo
4.4.3 Cyclic Dependency Behavior in Lean PlanDo

Learn why the "potential cyclic dependency" occurs in Lean PlanDo

Leanstation Support avatar
Written by Leanstation Support
Updated over a week ago

Cyclic dependency occurs when an activity/task is already a successor to another, and tries to be a predecessor at the same time. Even if the activity/task is not a direct successor of another, if they have successor activities in between, the same behavior will happen.

Cross-dependencies are dependencies between tasks from different activities.

The dependencies of activities are dominant over those of tasks, in the case of cross-dependencies. By dominant, we mean that if Activity 1 is a predecessor of Activity 2, then all tasks under Activity 1 are also predecessors of Activity 2.

Fig. Cyclic Dependency when trying to make 2c as predecessor of 1c

In this example, Activity 1 is a successor of Activity 2. Therefore, inherently, Tasks 1a, 1b and 1c are all predecessors of Tasks 2a, 2b and 2c. Thus, when we try to make 2c as a predecessor of 1c, cyclic dependency occurs and the error message is shown.

Did this answer your question?