See how your job is really performing, line by line. The Cost Category view on your job page puts estimated and actual costs side by side for every cost category and item, so you can spot what's over budget without clicking between screens.

Job Costing on the Redesigned Jobs Page

  1. Open a job in the redesigned Job Detail page.
    ​

  2. Go to the Work Details tab and toggle to Cost Category
    ​

    1. Each cost category has its own card: Labor, Equipment, Materials, Subcontractors, Other, and Overhead.

    2. The card shows progress (actual cost as a percent of estimated cost), actual cost, estimated cost, and variance.

    3. Labor also shows estimated and actual hours.
      ​

  3. Click a card to expand it and see the rows that make up its total.
    ​

What you'll see

  • Labor: one row per work area, with estimated and actual hours and cost.

  • Equipment, Materials, Subcontractors, and Other: one row per item, with the

  • work areas it's used on, estimated and actual quantity and cost, and variance.

  • Overhead: a single Overhead Costs row.

  • Variance is estimated cost minus actual cost. Green means you're at or under budget. Red, with a negative amount, means you're over. For example, estimated $2,307.19 and actual $374.00 shows a variance of $1,933.19.

  • Variance shows “--” when estimated cost is $0, actual cost is $0, or the two are equal.

  • “Unassigned” in the Work Area column means some of that item's actual costs weren't recorded against a work area. They still count toward the item's total.

  • The rows in a card add up to the card's total.

Notes

  • This view is read-only. To add or edit job costs, or to see the timesheets and vendor bills behind an actual, use the classic Job Costing page for now.

  • Estimated costs include any applied change orders.

  • The numbers match the Job costs widget and the classic Job Cost Overview.

  • A category with no items doesn't expand.

  • You need Job Costing access to see the Cost Category view. It isn't available on LMN Starter.


FAQs

Where did “View details” on the Job costs widget go?

The Cost Category sub-tab in Work Details replaces the job costs drawer. It shows the same category totals, plus the item-level detail the drawer didn't have. The rest of the Job costs widget is unchanged.

Can customers add or edit job costs in this view?

Not yet. The Cost Category view is read-only. To add manual costs or edit actuals, use the classic Job Costing page. Adding and editing job costs in Jobs 2.0 is planned for a future release.

Can customers click an actual to see the timesheet or vendor bill behind it?

Not yet. That's planned for a future release. For now, use the classic Job Costing page to trace an actual back to its timesheets, vendor bills, or manual entries.

Will these numbers match the classic Job Cost Overview?

Yes. Estimated, actual, and variance use the same data and calculation as Classic. Actuals include timesheets, vendor bills, and manual entries added in Classic. The one difference is that Jobs 2.0 also shows variance on each item row, while Classic shows it only on category totals.

Why does Overhead show 100% with no variance?

Overhead isn't tied to a timesheet or bill on the job. LMN applies it from the Operating Budget's overhead recovery, using the same amount for estimated and actual, so the two match and variance shows “--”. This is the same logic as the classic Job Cost Overview.

Do change orders show up?

Yes. When a job has an applied change order, estimated values come from it. Otherwise they come from the job's linked estimate.

Why can't a customer see the Cost Category sub-tab?

Check their Job Costing permission and package. Users with Job Costing set to No Access, and LMN Starter accounts, see Work Details as before, with no Work Area / Cost Category toggle.

Can customers see estimated vs. actual on the Work Area sub-tab?

Not yet. The Work Area sub-tab shows estimated values only. In the Cost Category view, Labor is broken out by work area. Comparing all costs by work area is planned for a later release.

Does this change the classic Jobs page?

No. These changes are only on the Jobs 2.0 job page.