Quick steps - Existing Tasks

1. Go to the Deliverables section

2. Find your deliverable

3. Click the three dots (⋮) menu

4. Select "Edit"

5. Update the due date

6. Save your changes

Note: This will only change the due date of currently assigned tasks. If you want the date changes to apply to any future tasks, go to the edit deliverables side pane to edit.

Quick steps - Recurring/Going forward tasks

  1. Go to Deliverables section sidebar on the right

  2. Find your deliverable

  3. Click the three dots (⋮) menu

  4. Select "Edit"

  5. Select "Schedules"

  6. Update the schedule

  7. Save your changes

Quick Steps - Assigning tasks to the past

  1. Go to Deliverables section sidebar on the right

  2. Find your deliverable

  3. Click the three dots (⋮) menu

  4. Select "Assign task"

  5. Select the desired date

  6. Verify the expected tasks are created