All West Maui customers who could have their power restored have been brought back online in the area. For returning customers looking to start the rebuilding process on their parcels, either with temporary or permanent electrical service, please see the following presentation provided by Hawaiian Electric representatives at the Lahaina Homeowners Meeting on Sept. 26, 2024 (timestamp at 46:00).
For more on the customer interconnection process, please visit Hawaiian Electric’s Upgrade, Modify, or Install Service web page or call Hawaiian Electric's Customer Installations at (808) 871-2390 or email ci@hawaiianelectric.com. Hours: Monday to Friday, 7 a.m. to 3:30 p.m.
For more information, visit Rebuilding West Maui | Hawaiian Electric
Rebuilding Electrical Infrastructure in Lahaina
Safety is our #1 priority
New upgraded poles and equipment
Rated for regulated safety standards under the National Electrical Safety Code (NESC)
Rated for higher wind gusts
Protective mesh on poles
Fire-safe devices
Weather stations + AI Cameras
Working with County on restoring streetlights
Long-Term Energy Planning
Working with the Lahaina community and government officials on long-term plans for Lahaina that would include the potential to strategically underground electric lines in the future.
Seeking more federal funding opportunities
Restoring Electrical Service to Your Property
Returning Customers: Customer on the electrical account before August 2023
To expeditiously power sites requesting electrical service, infrastructure will be rebuilt to what previously served the respective area at this time
Starting a Service Request
Triggers the rebuild in your area
Recommend starting with a Certified Electrical Contractor
Customer Interconnection Tool (CIT): www.hawaiianelectric.com