Summary
This article provides guidance on the steps to take when moving into, reconnecting or moving out of a site.
More info
Moving in
For sites without a previous connection, contact Origin eight weeks ahead to arrange a meter or confirm your provider. For sites with an existing meter, call four weeks before moving in, ensure meter access, and specify activation time. Disconnected sites over 12 months may need a safety inspection.
Reconnecting
Call Origin one week before reconnection. If disconnected for over 12 months, consult a Registered Electrical Contractor for safety compliance. Reconnection usually happens within five business days if your contract remains unchanged.
Moving out
Notify Origin six weeks before moving out. Disconnect the site if needed, complete the move-out form and review your Electricity Supply Agreement for any applicable charges.