Once a key date has been met you can mark it as complete, allowing you to focus on outstanding and upcoming key dates.

Once an item is marked as complete, it is removed from the Procurement Hub view, as the system prioritizes displaying only active or ongoing items for better organization.

How to mark as date as complete

  1. On your relevant product line, select the 'Details' option to open an editing panel to the right hand side of your screen.

  2. Select the 'Procurement' tab at the top of the panel.

  3. Select the checkbox next to each date to mark it as complete.

πŸ’‘ Completed dates will not show within your Procurement hub and will be displayed differently within your Schedule Procurement tab. You can easily unmark an item as complete by un-checking the box next to the associated date.