Use WBS Sync

Define the start and finish dates for each plan in Touchplan by identifying the phases in the master project schedule that need to sync.

Michael Sullivan avatar
Written by Michael Sullivan
Updated over 3 years ago

Our integration gives users the ability to define the start and finish dates for each phase plan in Touchplan by identifying the phases in the master project schedule they would like to sync with. The start and end dates can be updated in Touchplan at any time by re-syncing with the current master schedule start and end phase dates.

How To use WBS Sync

  1. Add a custom Field in your Schedule titled “Touchplan Phase” (Fig 1)

  2. Cut the the WBS Code, Touchplan Phase, WBS Name, Start Date & Finish Date (Fig 2)

  3. Save the file as a TXT file

  4. Open it in Notepad or TextEdit

  5. Then Copy and Paste it in the Synch WBS feature (Fig 3)

  6. See the Result (Fig 4 and 5)

Figures

Fig 1. Primavera Schedule sample with custom field added for Touchplan Phase sync.

Fig 2. Copy data from Master Phase Schedule and paste into Touchplan.

WBS Code   TouchPlan Phase     WBS Name                  Start                    Finish
1                     Green                       Sitework                        2020-01-17       2020-03-17
2                    Green                       Foundation - Bldg A     2020-03-17       2020-07-03
3                    Green                       Structure - Bldg A         2020-07-03     2020-10-31
4                    Green                       Weathertight - Bldg A   2020-11-18         2021-01-20
5                    Green                       Interior - Bldg - A           2021-01-20       2021-06-10
6                    Green                       Foundation - Bldg B      2020-06-18      2021-08-16
7                    Green                       Structure - Bldg B          2020-11-15        2021-02-02 
8                    Green                       Weathertight - Bldg B   2021-02-02       2021-04-15  
9                    Green                       Interior - Bldg - B           2021-04-15       2021-09-22


Fig 3. Sync / paste WBS data into this box.

Fig 4. Before and After WBS Sync.

Fig 5. Project Overview after WBS Sync.