The constraint log is a cumulative report of all constraints identified on a project.
"Constraint Description" column will be the description of the constraint as it is written in the plan
"Constrained Tasks" column, there will be a list of the tickets that are directly affected by the constraint- i.e. what will be delayed or unable to be completed until the constraint is complete
"Priority" column will show the three levels (On Track, Needs Attention & Critical) of status depending on progress towards removing the constraint and importance of the activities constraint
"Date Identified" column will show the date the constraint was created
"Requested By Date" column will show the day the constraint was requested to be completed by
"Planned Date" column will show the date that the user plans to complete the constrain by a user (this is done by opening the constraint to edit mode)
"Completed Date" column shows the date that the constraint has been completed
"Assigned To" column shows an individual who is responsible for the constraint
"Notes" column shows the notes that were typed into the constraint while it was in edit mode
How to run a Constraint Log:
Click on the Reports tab in the left side of the Plan View
Select Constraint Log from the Report type dropdown
Select the desired filters/layout
Click Run Report and then Open Report
The constraint log is able to be filtered by time period, by role, by plan, and by completion