All Collections
Admin User
Customize Project Work Week
Customize Project Work Week

Identify project workdays to create a default schedule each week

Carly Griffin avatar
Written by Carly Griffin
Updated over a week ago

Edit a Project Workweek to make sure the default schedule matches the project team's workdays.

How To Adjust the Work Week:

  1. Go to Settings on the left-hand side.

  2. Open Project Work Schedule.

  3. Select and Deselect the boxes on the days of the week to identify as workdays vs. nonworkdays.

How to add a Holiday:

  1. Go to Settings on the left-hand side.

  2. Open Project Work Schedule.

  3. Click Add Non-work Day.

  4. Enter a name and date of a non-workday and click save.

Note: Only Admins can edit the Work Schedule. Edit the Custom Role Work Schedule if specific roles work different schedules than others.

Did this answer your question?