Task Workdays

Customize which days on individual tasks are classified as workdays or non-workdays

Written by Jason Lyon

Use Task Workdays to identify what days work has actually happened or what days work is planned to happen on individual tasks.

How to customize workdays on a single task:

  1. Click to open a task ticket's edit window.

  2. Toggle the green lights above each day on or off to indicate if work is planned to happen on that day (Green= Workday, White= Non-workday).

  3. Click save when done.

Note: Use Ticket Workdays to identify 'one-off' scenarios throughout the schedule. To make universal changes to workdays across a project, refer to Project Work Schedule or Role Work Schedules under settings.