Start Work in Touchplan
Start Work in Touchplan
Carly Griffin avatar
Written by Carly Griffin
Updated over 6 months ago

Indicate that a task has started but has not yet been completed:

  1. Right-click on the task ticket

  2. Select Start Work

  3. The Planned Start date will be locked in as the actual start date

When you run reports the actual start date will be included when applicable.

Started activities will allow the team to better understand how they are working through the current week of work.

Note: If the actual start date is different from the planned start date. Replan the activity to the correct start date before selecting "Start Work"