How does rescheduling requests work?

What happens when a supplier ships a different quantity than planned, and how the buyer handles it.

A shipment rescheduling request is created when a supplier ships a different quantity than planned in the order line's delivery schedule. It makes sure the buyer always knows about the difference and can decide whether to accept it.

When is a rescheduling request created?

Automatically, when a supplier issues or reissues a shipment and the shipped quantity doesn't match the quantity in the delivery schedule of the related order line. If the quantities match, no request is created.

What the buyer sees

  • A notification.

  • An open rescheduling request on the order line and on the related shipment.

[Image to add: an open rescheduling request on the order line]

How the buyer handles it

  1. Open the order line.

  2. Review the rescheduling request.

  3. Approve or reject it.

Important

  • Approving or rejecting the shipment does not approve or reject the rescheduling request.

  • Rescheduling requests are always handled from the order line, not from the shipment.