How to extend valuation schedule

Error - No Valuation dates have been set for this order. Please contact Qs

A
Written by Artur Brzostowski
Updated over a year ago

When Valuation Schedules runs out users trying to add application for payment will see below error:

In this instance QS is required to extend Project End Date and update Valuation Schedules for the Project.

  1. Open required Project and go to Valuation Schedules Tab and extend Project's End date:

  2. Click Confirm in New Window:

  3. Edit individual Valuation and Submission dates as required:

  4. When finished click Save: