Enabling dependencies in your WeTrack system

Admin users can turn on the dependencies setting to enable users to be able to make tasks dependent on one another. This enables action owners of dependent tasks to be notified when things change on a task that might affect them.

To turn on dependencies, navigate to Settings > Projects & Risks > Dependencies, and check the box.

Click here for a full introduction to dependencies, and click here to see how you can use dependencies in the Gantt chart.