Critical Path in the Gantt

Viewing your projects' critical path

Leoni Keogh avatar
Written by Leoni Keogh
Updated over a week ago

Within the Gantt, you can view a highlighted Critical Path.

A Critical Path is a sequence of Tasks that cannot be delayed. They rely upon each other’s on-time completion, and a delay would lead to Dependencies jeopardising the entire timeline. A delayed Critical Path means a delayed Project.

A Task is considered Critical if it has no days of slack and any delay would directly affect the Project completion date. Slack time is the time that a Task can slip without affecting other Tasks or the Project’s completion date.

Simple toggle the Critical Path on or off in the ‘Gantt Options’ bar.